Planned Electricity Outage Notice: Clanwilliam
Date: Wednesday, May 14, 2025
Time: 08:00 - 17:00 (approximately 9 hours)
Areas Affected:
- Middedorp Feeder:
- Augsburg farm
- Park Street (north and south)
- Bosassa Youth Care Centre
- Ramskop Abattoir
- Jan Dissel water pump station
- Milner Street sewer pump station
- De Vlei Feeder:
- MS-Mark area
- Reƫnblom
- Skool Street
- Augsburg Agricultural Gymnasium
- Rev. Brooke area
- De Vlei
- Park Sub area
- Plain Street
- Visser Street
- Hotel area
- Foster area
Businesses Affected:
- Along Augsburg Road
- Along Graafwater Road
- Along Main Road
- Along Visser Road
- Along Voortrekker Road
Reason: Contractor work at Mark mini substation and Milner Street MV overhead line, and municipal electrical team work at the mini substation and RMU at the Hotel.
Important Safety Notice:
- All installations should be regarded as live.
- No generators should be connected without consent.
We apologize for the inconvenience and appreciate your understanding as we work to maintain and improve our electrical infrastructure.
Last published 08 May 2025